The major deliverable when closing out a project that includes a causal analysis and identification of lessons learned is known as


A) Wrapping up a Project.
B) Project Audit.
C) Evaluation of Performance.
D) Evaluation of Management.

E) A) and D)
F) All of the above

Correct Answer

verifed

verified

Before an evaluation of the project team can be effective and useful, a minimum core of conditions needs to be in place before the project begins.Which of the following would NOT be one of those conditions?


A) Individuals have the skill set necessary to successfully complete the project
B) Evaluation criteria beyond time, cost and specifications has been established
C) Rewards are adequate
D) Individual, team responsibilities and performance standards are known by all team members
E) Standards for measuring performance exist

F) C) and D)
G) D) and E)

Correct Answer

verifed

verified

The ____________ report summarizes project performance and provides useful information for continuous improvement.

Correct Answer

verifed

verified

final
Explanation: The final report summ...

View Answer

Which part of the final report examines in detail the underlying causes of problems, issues, and successes relative to the project and includes concise, factual review statements of the project?


A) Executive summary
B) Review and analysis
C) Recommendations
D) Lessons learned
E) Appendix

F) B) and D)
G) A) and E)

Correct Answer

verifed

verified

In order for lessons learned to be effective and usable by others a(n) ___________ needs to be assigned to assure it is properly documented and understood.


A) Stakeholder
B) Owner
C) Project Manager
D) Software Developer

E) A) and B)
F) B) and D)

Correct Answer

verifed

verified

When performing a retrospective for a project, whoever is performing the retrospective needs to be perceived as being independent and unbiased.

A) True
B) False

Correct Answer

verifed

verified

When conducting post-project audits, this is one of the main tools that a facilitator uses.


A) A final copy of the issues log
B) A review session regarding the project scope
C) Questionnaires
D) The Earned Value analysis

E) A) and D)
F) B) and C)

Correct Answer

verifed

verified

The following are general tips for conducting performance reviews EXCEPT


A) Begin the process by asking the individual to evaluate his or her own contributions to the project.
B) Use other team members' performance as a method to compare and evaluate.
C) When you have to be critical, focus the criticism on specific examples of behavior and not on the individual personally.
D) Be fair and consistent in your treatment of all team members.
E) Treat the review as only one point in an ongoing process.

F) C) and D)
G) B) and D)

Correct Answer

verifed

verified

Perhaps the _________ section of the final report is the most valuable contribution of the closure process.

Correct Answer

verifed

verified

lessons learned
Explanation: P...

View Answer

Which part of the final report presents major improvement actions that should be made?


A) Executive summary
B) Review and analysis
C) Recommendations
D) Lessons learned
E) Appendix

F) A) and C)
G) B) and D)

Correct Answer

verifed

verified

A 360-degree performance evaluation includes feedback from peers, project managers, subordinates, and even customers.

A) True
B) False

Correct Answer

verifed

verified

A guide who leads the project team through an analysis of project activities that went well and of what needs improvement and development of a follow-up action plan with goals and accountability is known as a project ____________.

Correct Answer

verifed

verified

facilitator
Explanation: The retrospecti...

View Answer

Completing Team Evaluations relies upon ____________ to be in place before the project begins.


A) A completed scope document
B) Budget constraints
C) Quality controls
D) Core of conditions

E) C) and D)
F) A) and B)

Correct Answer

verifed

verified

__________ of lessons learned are designed to improve performance on current and future projects.


A) Retrospectives
B) Corrective action plans
C) Introspectives
D) Culminations
E) Evolutions

F) A) and E)
G) None of the above

Correct Answer

verifed

verified

The key requirement in selection of the facilitator is one who is the end-user.

A) True
B) False

Correct Answer

verifed

verified

Within the final report, the project summary is the summary that simply highlights the key findings and facts relating to the project implementation.

A) True
B) False

Correct Answer

verifed

verified

Motivation can be the chief challenge when wrapping up closure activities.

A) True
B) False

Correct Answer

verifed

verified

The most common reason given for not creating lessons learned is the lack of _________.

Correct Answer

verifed

verified

time
Explanation: The processes for capt...

View Answer

The retrospective methodology is more inclusive and disciplined than past lessons learned approaches.

A) True
B) False

Correct Answer

verifed

verified

The processes for capturing lessons learned continue to evolve, but there are still barriers to effectively mining lessons learned.

A) True
B) False

Correct Answer

verifed

verified