In "crashing",a project manager will generally focus on activities which:


A) are not on the critical path.
B) are the least costly to crash.
C) are costly to crash and are on the critical path.
D) are on the critical path and are the least costly to crash.
E) none of the choices are correct.

F) B) and E)
G) A) and B)

Correct Answer

verifed

verified

  -What are the estimated expected (mean)durations (in weeks)for activities A-H? -What are the estimated expected (mean)durations (in weeks)for activities A-H?

Correct Answer

verifed

verified

15; 20; 10; 35; 25; 30; 20; 5

Determine the amount of slack in each of a project's activities (see the list below),and identify those which are on the critical path. Determine the amount of slack in each of a project's activities (see the list below),and identify those which are on the critical path.

Correct Answer

verifed

verified

What is the estimated slack time for the path B-D-F?


A) 0 days
B) 30 days
C) 40 days
D) 50 days
E) 100 days

F) A) and E)
G) B) and D)

Correct Answer

verifed

verified

The standard deviation of the duration of the critical path is equal to the square root of the sum of the variances of all of the activities on the critical path.

A) True
B) False

Correct Answer

verifed

verified

Consecutive activities on the same path have shared slack,which means if activities are delayed,the amount of slack remaining is reduced for all these activities without delaying completion of the project.

A) True
B) False

Correct Answer

verifed

verified

The standard deviation of a project duration is equal to the sum of the variances of all the activities of the project.

A) True
B) False

Correct Answer

verifed

verified

The principal advantage a Gantt chart has over other project scheduling techniques is:


A) its ability to reveal relationships among activities.
B) it illustrates multiple paths as a project network.
C) it focuses on the critical path.
D) its simplicity.
E) both cost and time are included in the chart.

F) C) and D)
G) All of the above

Correct Answer

verifed

verified

The latest starting time for an activity is equal to the latest finish time minus the activity time.

A) True
B) False

Correct Answer

verifed

verified

True

Which of the following is not a form of risk reduction in project management?


A) Backup systems
B) Outsourcing components of the project
C) Frequent monitoring of project activities
D) Expand the project scope to reduce external dependencies
E) Improving communications

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

The project management strategy of injecting additional resources in order to reduce the length of the project is called:


A) expediting.
B) rushing.
C) panicking.
D) crashing.
E) none of the choices are correct.

F) All of the above
G) A) and D)

Correct Answer

verifed

verified

A hierarchical listing of what must be done during the project is called:


A) work breakdown structure (WBS) .
B) program evaluation and review technique (PERT) .
C) planning matrix.
D) crashing.
E) critical path method (CPM) .

F) A) and B)
G) C) and E)

Correct Answer

verifed

verified

What is the estimated standard deviation of the duration for activity E?


A) 2 days
B) 3 days
C) 4 days
D) 16 days
E) 24 days

F) C) and D)
G) B) and C)

Correct Answer

verifed

verified

  -What is the critical path for this project network? -What is the critical path for this project network?

Correct Answer

verifed

verified

The life cycle of a project includes which of the following phases? I.Initiation II.Planning and scheduling III.Growth and maturity IV.Closeout


A) I and II only
B) II and III only
C) I, II, and IV only
D) II, III, and IV only
E) I, II, III, and IV

F) B) and C)
G) None of the above

Correct Answer

verifed

verified

A PERT/CPM activity has an optimistic duration estimate of 3 days,a most likely duration estimate of 8 days,and a pessimistic duration estimate of 10 days.The expected duration of this activity te is:


A) 7.0
B) 7.5
C) 8.0
D) 8.5
E) 10.0

F) A) and D)
G) A) and C)

Correct Answer

verifed

verified

What is the probability that this project will be completed within 205 days?


A) 0.6826
B) 0.8413
C) 0.9544
D) 0.9772
E) 0.9987

F) A) and B)
G) A) and E)

Correct Answer

verifed

verified

What is the estimated slack time for the path A-D-F?


A) 0 days
B) 20 days
C) 40 days
D) 60 days
E) 100 days

F) All of the above
G) A) and B)

Correct Answer

verifed

verified

Purchase planning is typically outside the scope of project planning activities.

A) True
B) False

Correct Answer

verifed

verified

In the probabilistic approach to precedence network analysis,the duration estimate annotated "tm" for any activity is the:


A) mean duration.
B) median duration.
C) most likely duration.
D) optimistic duration.
E) pessimistic duration.

F) B) and D)
G) A) and D)

Correct Answer

verifed

verified

C